The Downtown Littleton Row Homes project is underway now, with an anticipated completion schedule of Spring 2020!

 

2018 - Conceptual design, permitting, site work.

2019 Q2 - Groundwork, site prep, excavation.

2019 Q3 - Foundation, utilities, flatwork.

2019 Q4 - Framing, building envelope.

2020 Q1 - Mechanicals, insulation.

2020 Q2 - Fixtures and finish.

 

Stay tuned for further updates about this exciting project!